Toolkit: Gantt chart

Exclusive content on Boosty, video classes on YouTube, summaries and notes on Instagram, units 1~5 content in the best free textbook, class extracts on TikTok, text below. Have fun!

Chapter contents:

  • How to — how the tool works
  • Pros and cons — evaluation of the tool
  • IA — how to apply the tool in IA
  • Example — sample IA extract with the tool

The main purpose of the Gantt chart is to show the timeline of the project.

Just a reminder to keep a record of all the tools in the table below. As long as you can fill in all the cells of the table, you will be able to write a successful IA.

How to

How the tool works

Gantt chart is a project management tool for visualising the timeline of project activities/tasks. Its purpose is to visualise the project timeline. Gantt chart is a relatively simple tool with only two main elements:

1. Activity (task) — one of the assignments in the project, indicated by horizontal bars.

2. Duration — how long the task takes (hours, days, weeks, months, etc.), indicated by the bar length.

There are 5 simple steps in preparing a Gantt chart. To illustrate all the steps, we’ll refer to a Bobo Pizza restaurant and its manager who finished the restaurant renovation but did not use any business tools for planning the renovation project. The manager just shut down the restaurant for one month and did all the renovation based on his feelings, without any system. We’ll see if the manager could have saved some time if he used a Gantt chart.

First of all, it is necessary to identify all project activities/tasks.

Figure 1. Identifying the project tasks

After that, we put all the tasks in order. In this case, we just label them from A to G.

Figure 2. Ordering the tasks

Then, we identify dependencies and durations. Let’s say we talked to the Bobo Pizza restaurant manager and he said that installing new equipment can only start after the old one is removed. Besides, new furniture in the dining area can only be assembled after the walls are painted and old furniture is removed. The manager and staff also said how long each of the tasks took.

Figure 3. Identifying dependencies and durations

Now we have everything we need to construct the Gantt chart for the Bobo Pizza renovation. Based on the previous step...

Read full chapter and watch full video class here: